MDOT has announced that they are updating their e-Proposal website with a more modern look. The information provided will be the same, but accessing and navigating the website will be different. These changes will take place on September 7, 2017. All e-Proposal users will need to ensure they have a
MDOT has announced that they are updating their Progress Schedule (Form 1130) requirements. Effective with the November 3, 2017 letting, all Progress Schedule submittals must occur after project award. This change was requested by the Federal Highway Administration to ensure that negotiations do not occur prior to project award. The
What a difference a couple of weeks can make. During the MITA summer conference, we reported to the Board of Directors that electronic reporting of OSHA logs (300, 300A and 301) of high hazard industries like ours will be required to be done on OSHA’s website. The electronic reporting rule